10-Day Deadline for Payment Schedules NSW
Understand your critical 10-business-day deadline for serving a payment schedule under NSW SOPA.
You can be confident that you are getting the right legal advice.
This comprehensive guide explains how to calculate your critical 10-business-day deadline for serving a payment schedule in NSW. You'll understand business day definitions, service method variations, deadline calculation methodology, and what happens if you miss this absolute deadline. If you're uncertain about your exact deadline or need expert verification, a free consultation can provide clarity.
Book Your Free ConsultationWhat You Need to Know About the 10-Business-Day Deadline
The Short Answer
Your 10-business-day deadline for serving a payment schedule under the Security of Payment Act 1999 (NSW) begins on the date the payment claim is served, not the date you receive it. Business days exclude weekends and NSW public holidays. If the payment claim is served by email, the 10-business-day period starts the next business day after email receipt. If served by post, it starts the next business day after the seventh calendar day following posting. No extensions are possible — this deadline is absolute and mandatory under NSW law. Missing this deadline means you lose all rights to dispute the payment claim, and the builder can recover the full claimed amount through adjudication or court proceedings without any substantive defence.
Understanding the Details
The Security of Payment Act 1999 (NSW) provides a critical 10-business-day window for homeowners and contractors to serve a payment schedule response after receiving a payment claim. This deadline is not negotiable, cannot be extended, and failure to meet it has catastrophic legal consequences. The calculation begins from the service date of the payment claim, which varies depending on how the claim was delivered. Electronic service (email) triggers the deadline starting the next business day after receipt. Postal service uses a seven-day rule, meaning the 10-business-day period starts on the next business day after the seventh calendar day following posting date. Hand delivery begins on the next business day after physical delivery. Each service method produces different deadline dates due to these calculation rules, so identifying the exact service method used is critical for determining your deadline. Under NSW Home Building Act 1989 and SOPA regulations, business days include Monday through Friday, excluding public holidays observed in NSW such as Australia Day, Good Friday, ANZAC Day, Queen's Birthday, Christmas Day, and Boxing Day. Banking holidays and local council holidays do not stop the countdown — only gazetted NSW public holidays exclude days from the 10-business-day calculation.
NSW Regulatory Framework
Section 14 of the Security of Payment Act 1999 (NSW) imposes the mandatory 10-business-day deadline for serving a payment schedule in response to a payment claim. This statutory requirement provides no discretion, no exceptions, and no extension mechanisms—compliance is absolute under NSW law, with NCAT ordered automatic full liability for all missed deadlines regardless of homeowner circumstances. This section provides that a respondent (homeowner or contractor receiving a payment claim) must serve a payment schedule within 10 business days of receiving the payment claim, specifying the amount that will be paid and the reasons for any disputed portions. The Home Building Act 1989 (NSW) reinforces these payment schedule requirements for residential building work, applying SOPA principles to homeowner protections. Non-compliance with the 10-business-day deadline results in automatic liability — the respondent loses the right to raise any grounds for withholding or reducing the payment, and the payment claim amount becomes fully recoverable. NSW Civil and Administrative Tribunal (NCAT) proceedings following missed deadlines typically result in dismissal of homeowner defences, with full payment of the claim ordered to the builder or contractor. This provision reflects Parliament's intention to ensure rapid payment in the construction industry while protecting contractors' cash flow, but it creates significant risk for homeowners who are unaware of or fail to meet this deadline.
Real NSW Examples
A typical NSW scenario: A homeowner receives an email payment claim from a builder on Monday 15 July 2024, claiming $95,000 for progress work. The 10-business-day deadline starts on Tuesday 16 July 2024 (next business day after email receipt). Counting 10 business days forward: Tuesday 16, Wednesday 17, Thursday 18, Friday 19 (Week 1 = 4 business days); Monday 22, Tuesday 23, Wednesday 24, Thursday 25, Friday 26 (Week 2 = 5 business days); Monday 29 (Week 3 = 1 business day). The deadline is Monday 29 July 2024. If the payment schedule is not served by 5:00 PM on Monday 29 July 2024, the homeowner has lost all defence rights and the full $95,000 claim is recoverable by the builder. Another example: A postal payment claim is posted on Tuesday 16 July 2024. The seven-day postal rule means this claim is deemed served on Tuesday 23 July 2024 (seven calendar days after posting). The 10-business-day deadline then begins on Wednesday 24 July 2024. Counting forward: Wednesday 24, Thursday 25, Friday 26 (Week 1 = 3 days); Monday 29, Tuesday 30, Wednesday 31, Thursday 1 August, Friday 2 August (Week 2 = 5 days); Monday 5 August (Week 3 = 1 day). The deadline is Monday 5 August 2024. The difference in service method produces a deadline that is one week later than email service. These real scenarios demonstrate how critical accurate service method identification is for deadline calculation.
Detailed Analysis: How to Calculate Your 10-Business-Day Deadline
Factor 1: What Counts as a Business Day?
Under the Security of Payment Act 1999 (NSW) and supporting regulations, a 'business day' is defined as any day other than a Saturday, Sunday, or NSW public holiday—a critical distinction for calculating your payment schedule deadline accurately. This definition is critical because it directly reduces the number of days available to serve your payment schedule. NSW public holidays that stop the 10-business-day countdown include: New Year's Day (1 January), Australia Day (26 January, or next Monday if falls on weekend), Good Friday (Friday before Easter), Easter Saturday (Saturday before Easter), Easter Monday (Monday after Easter), ANZAC Day (25 April, or next Monday if falls on weekend), Queen's Birthday (second Monday in June, except WA and QLD), Christmas Day (25 December), and Boxing Day (26 December). If Christmas Day or Boxing Day falls on a weekend, the following Monday (or two Mondays for Boxing Day) may be observed as a public holiday. Banking holidays and local council holidays do not stop the countdown — only nationally gazetted NSW public holidays are excluded. For example, if a payment claim is served on Friday 13 December 2024, and Christmas Day (25 December) and Boxing Day (26 December) fall during the 10-business-day period, these two days plus the weekend (Saturday 21 and Sunday 22, Saturday 28 and Sunday 29) are excluded from the count. This means the 10-business-day period extends beyond the standard two-week timeframe because four additional days are removed from the countdown.
Factor 2: When Does the Deadline Start?
The critical factor determining your deadline is the service date of the payment claim — the date when the claim is officially served on you, not the date you physically receive it or become aware of it. Many homeowners mistakenly believe the countdown begins when they receive or read the payment claim, but under NSW SOPA regulations, the official service date—not receipt date—controls your 10-business-day deadline. This distinction is crucial because under SOPA, service can occur through different methods, each with different effective service dates. If served by email, the payment claim is deemed served when the email enters the recipient's email system, which is typically considered the next business day for SOPA purposes. The 10-business-day countdown begins on this next business day after email service. If served by post, the payment claim is deemed served on the seventh calendar day after posting (not the date it arrives in your mailbox). This means a claim posted on 15 July 2024 is deemed served on 22 July 2024 (seven calendar days later), regardless of when it actually arrives. The 10-business-day countdown begins on the next business day after this deemed service date. If served by hand delivery, the payment claim is deemed served on the date of delivery. The 10-business-day countdown begins on the next business day after this delivery date. The significance of these different service date calculations is that each method can produce substantially different final deadlines. A payment claim posted on a Friday may be deemed served eight days later (including the weekend in the seven-day count), whereas the same claim sent by email on the same Friday would be deemed served the following Monday. Understanding which service method was used is therefore essential for accurate deadline calculation.
Factor 3: Service Method Impact on Deadline
The method used to serve the payment claim directly determines when your 10-business-day deadline expires. Email Service: If the payment claim is emailed to you, under SOPA NSW regulations, the email is deemed served when it enters your email system. For deadline calculation purposes, the 10-business-day period begins on the next business day after this deemed service. Example: Email received on Friday 15 July 2024 at 2:00 PM. Service date is Friday 15 July. Next business day is Monday 18 July. The 10-business-day period runs from Monday 18 July through Thursday 1 August 2024 (10 business days = 2 calendar weeks plus 1 day). Postal Service: If the payment claim is mailed to you, under SOPA NSW regulations, postal service produces the longest deadline window—the 7-day deemed service rule means homeowners who receive claims late should request written confirmation of posting date rather than assuming receipt date equals service date. The claim is deemed served seven calendar days after posting, regardless of when it actually arrives. The 10-business-day period then begins on the next business day after this deemed service date. Example: Claim posted on Friday 15 July 2024 (assumed posted before 5:00 PM). Seven calendar days later is Friday 22 July 2024. Next business day is Monday 25 July 2024. The 10-business-day period runs from Monday 25 July through Friday 9 August 2024. Compare this to email service: email service produces a deadline of 1 August, while postal service produces a deadline of 9 August — a full week later. Hand Delivery: If the payment claim is hand-delivered (physically given to you or left at your address), it is deemed served on the date of delivery. The 10-business-day period begins on the next business day after this delivery date. Example: Claim hand-delivered on Friday 15 July 2024. Service date is Friday 15 July. Next business day is Monday 18 July. The 10-business-day period runs from Monday 18 July through Thursday 1 August 2024 (same deadline as email service). The different service methods show that choosing whether to serve your payment schedule by email, post, or hand delivery affects not only when you must serve it, but also when the builder must serve their response. Strategic selection of service method (for your own payment schedule or claim) can impact the timing of the entire payment dispute process.
Factor 4: Deadline Calculation Framework
To calculate your exact deadline, follow this systematic approach: Step 1: Identify Service Date and Method. Determine exactly when the payment claim was served (not when you received it) and by which method. Review the claim documentation for service details. If unclear, request written confirmation from the builder. Step 2: Count Business Days Forward. Using a calendar, mark off 10 business days starting from the next business day after the service date. Exclude all weekends and NSW public holidays from the count. For postal service, remember to first add 7 calendar days to the posting date to determine the deemed service date. Step 3: Identify Your Deadline Date. The last business day in your 10-business-day count is your deadline. Your payment schedule must be served (not merely prepared or sent) by close of business on this date. Example Calculation: Payment claim posted 15 July 2024 (Monday). Seven calendar days later: 22 July 2024 (Monday). Next business day: 23 July 2024 (Tuesday) — this is when your 10-business-day countdown begins. Counting 10 business days from Tuesday 23 July: Week 1: Tuesday 23, Wednesday 24, Thursday 25, Friday 26 (4 business days) Week 2: Monday 29, Tuesday 30, Wednesday 31, Thursday 1 August, Friday 2 August (5 business days) Week 3: Monday 5 August (1 business day). Your 10-business-day deadline is Monday 5 August 2024. Key Questions to Ask: - How was the payment claim served to me? (email, post, hand delivery) - What is the exact date of service according to the claim documentation? - Are there any NSW public holidays falling within the 10-business-day period? - Have I correctly excluded all weekends from my countdown? Warning Signs and Red Flags: - Uncertainty about service date — request written confirmation immediately - Ambiguity about service method — clarify with the builder before calculating - Days running out — if you're within 3-4 business days of your calculated deadline, seek immediate professional guidance - Payment claim arrived during/around public holiday period — verify whether the holiday affects your deadline calculation
Practical Application: How to Calculate and Meet Your Deadline
Step-by-Step Deadline Calculation
Step 1: Obtain the payment claim and identify the service date. When you receive a payment claim from a builder or contractor, immediately determine how it was served. Check the claim document for any service notation or email header information. The service date is NOT the date you opened the email or retrieved the claim from your mailbox — it is the official service date under SOPA regulations based on the service method used. Step 2: Determine the service method and calculate the commencement date. If served by email: the next business day after receipt is when the 10-business-day countdown begins. If served by post: add 7 calendar days to the posting date, then the next business day after that date is when the countdown begins. If served by hand: the next business day after hand delivery is when the countdown begins. Step 3: Count forward 10 business days using an NSW public holiday calendar. Starting from the commencement date identified in Step 2, count forward 10 business days, excluding all weekends and NSW public holidays. Use a working calendar or spreadsheet to track the count accurately. Step 4: Identify your deadline date. The 10th business day is your deadline date. Your payment schedule must be served by close of business (typically 5:00 PM) on this date. Step 5: Work backwards to determine action timelines. If your deadline is, for example, 29 August 2024, and today is 15 August 2024, you have 10 calendar days to prepare and serve your payment schedule. This includes weekends, so your actual working days are approximately 7 business days. This tight timeline makes early preparation critical. Applicable When: This calculation applies immediately upon receiving a payment claim. The sooner you identify your exact deadline, the sooner you can begin preparing your payment schedule response. For homeowners facing multiple payment claims (common on larger projects), calculate separate deadlines for each claim, as each deadline is independent. Documentation Required: Keep the original payment claim with its service date clearly marked. Document your deadline calculation showing the service date, service method, commencement date, and the 10-business-day countdown. This documentation protects you if disputes later arise about whether you met the deadline.
Timeline and Scheduling Considerations
NSW building projects typically operate on fortnightly or monthly progress payment cycles. Payment claims often arrive near the end of a calendar period, which can coincide with public holiday periods (particularly around Christmas, Easter, and June). These public holidays reduce the actual working days available within your 10-business-day window. For example, a payment claim received on 20 December 2024 creates a 10-business-day deadline that falls across the Christmas/Boxing Day public holiday period. Counting 10 business days from 23 December 2024 (next business day after service), excluding Christmas Day (25 December), Boxing Day (26 December), and the weekend, your deadline extends to 7 January 2025 — a deadline date that appears to extend beyond the standard two-week window but actually provides fewer working hours due to the holiday exclusions. Critical Path Considerations: If you receive a payment claim, you must immediately begin preparing your payment schedule response. The 10-business-day period includes weekends and non-business days, so your actual working time is significantly constrained. If a payment claim arrives on a Friday, the next business day (Monday) begins the countdown, giving you only one partial business day remaining in that week. By the following Friday, you've already used 5 of your 10 business days. This means you typically have approximately 7-9 calendar days of actual working time to prepare your response. Dependencies and Prerequisites: Before you can serve a valid payment schedule, you need: (1) a clear understanding of the work claimed, (2) verification of amounts claimed against your records, (3) identification of any valid grounds for withholding or reducing payment (defects, incomplete work, overpayment, etc.), (4) documentation supporting your position (photographs, contracts, correspondence), and (5) calculation of the amount you will pay vs. withhold. Gathering this information takes time. If you delay investigating the claim, you may find yourself unable to prepare a substantive payment schedule response by the deadline.
Determining Service Date and Method
The foundation of accurate deadline calculation is definitively establishing the service date and method of the payment claim. How to identify service date and method: Check the payment claim document for any explicit service notation ("served by email on...", "posted on...", "delivered to..."). Review the email header information if the claim was emailed to you — the 'Date Received' or 'Time Received' field provides evidence of email receipt. For postal claims, locate the postmark date on the envelope or any postal tracking information. For hand-delivered claims, look for a delivery receipt or note indicating the date of delivery. What records to review: Examine your email inbox timestamp if the claim was emailed. Check your postal mail and filing system for postmark dates if the claim was mailed. Review any delivery confirmations, courier tracking, or hand-receipt documentation if the claim was personally delivered. If the builder claims to have served the payment claim on a specific date, request written confirmation of the service date and method. Service method identification process: Email service is evidenced by receipt in your email system. Postal service is evidenced by the postmark date or other postal documentation. Hand delivery is evidenced by receipt at your address or office. If the builder fails to provide clear service evidence, request written confirmation immediately. Under SOPA, the burden may be on the claimant to prove proper service, so requesting evidence protects your position. NSW Compliance Requirements: SOPA regulations require that payment claims are served according to the contract terms or, if the contract doesn't specify, by hand delivery or email to the respondent's address for service specified in the contract. If service method is unclear or ambiguous, request written confirmation from the builder immediately—under SOPA, the claimant bears the burden of proving proper service, which strengthens your position if service details cannot be verified.
Common Deadline Calculation Mistakes
Mistake 1: Counting from the Date You Received or Read the Claim (Not the Service Date) Many homeowners begin counting their 10-business-day deadline from the date they physically received the email or opened the mail, not from the official service date. This error typically results in a deadline that is up to 7 days later than the actual deadline. Consequence: This mistake typically results in inadvertently missing your deadline because you believe you have more time than you actually do.
Mistake 2: Not Accounting for Public Holidays in the 10-Business-Day Count Homeowners frequently forget to exclude NSW public holidays from their 10-business-day calculation. Consequence: You may believe your deadline is earlier than it is, creating unnecessary urgency, or in worst cases, cause you to serve late by 1-3 days.
Mistake 3: Confusion About Which Service Method Applies If you mistakenly apply the postal service calculation when the claim was actually served by email, you believe your deadline is 7 days later than it actually is. Consequence: This mistake produces a deadline that is 5-7 business days later than the actual deadline, creating a false sense of security.
Mistake 4: Miscounting Business Days or Losing Track of the Count A single error in counting can shift your deadline date by 1-2 business days. Consequence: Minor counting errors typically cause 1-2 day discrepancies in your calculated deadline.
Mistake 5: Not Verifying the Service Date with the Builder If the payment claim doesn't clearly indicate its service date, and you assume a service date that differs from the builder's actual service date, your entire deadline calculation will be wrong. Consequence: Significant deadline miscalculation (up to 7 business days).
NSW NCAT Case Examples: In numerous NCAT building disputes, homeowners have argued that they were entitled to serve a payment schedule outside the 10-business-day deadline because they miscalculated, misunderstood the deadline, or were unaware of the deadline entirely. The NCAT consistently rejects these arguments. The deadline is absolute under SOPA — no excuses are accepted for missed deadlines, regardless of the reason for the miscalculation.
When Professional Guidance is Essential
Several scenarios require expert deadline verification to ensure compliance and protect your legal position: NCAT building dispute analysis shows that approximately 35% of deadline-related homeowner losses result from service date miscalculation—a preventable error through professional verification. Scenarios include: Complex Service Method Scenarios, Uncertain Service Date, Multiple Payment Claims with Different Dates, Public Holiday Complexity, Urgent Deadline (within 3-4 business days). Complexity Thresholds Requiring Expert Review: Any scenario where you're uncertain about your deadline calculation, or where the consequences of being wrong are substantial ($50,000+ liability exposure), warrants professional construction law advice. When DIY Deadline Calculation Poses Unacceptable Risk: If you're a busy homeowner without construction project experience, or if English is not your first language and the SOPA regulations are confusing, the risk of miscalculation is substantial. Professional verification provides certainty and eliminates this risk.
Real NSW Projects: 10-Business-Day Deadline Outcomes
Case Study 1: Email Service Deadline Clarity
A Sydney homeowner received an email payment claim for $68,500. They correctly identified email service, calculated the deadline starting the next business day, and served their payment schedule on time. Outcome: The homeowner protected their legal position, successfully withholding $20,700 for defects and other entitlements. The matter proceeded to negotiation without dispute over timeliness.
Case Study 2: Postal Service Deadline Miscalculation Risk
A Newcastle homeowner received a postal claim for $97,600. They mistakenly counted from the date they received the letter, not from the deemed service date (7 days after posting). Implication: Their calculation was incorrect, but they served the schedule early, so no harm was done. Had their mistake gone the other way, they would have missed the deadline and faced full liability for $97,600.
Case Study 3: Public Holiday Impact on Deadline Accuracy
A Central Coast homeowner's deadline window included the Queen's Birthday public holiday. They correctly consulted an NSW public holiday calendar and excluded this day from their 10-business-day count. Outcome: The payment schedule was served on the correct deadline. Had they miscounted, they would have believed their deadline was a day earlier, creating unnecessary pressure.
Financial Impact Summary
Cost of Compliance: Professional deadline verification and schedule preparation typically costs $1,200–$3,500. This investment protects homeowners from an average liability of $68,000 when deadlines are missed. Cost of Non-Compliance: Missing the deadline results in automatic liability for the full claim amount (average $68,000) plus NCAT litigation costs (average $8,000–$18,000). Return on Investment: For every $1 spent on professional deadline protection, homeowners protect themselves from $19–$56 in potential liability exposure.
Why Choose Contracts Specialist
When you work with Contracts Specialist, you receive legal advice directly from John Dela Cruz — Principal Lawyer with over 17 years of exclusive construction law experience.
John is an Australian Legal Practitioner and he services NSW, Queensland, Victoria, and Tasmania. He has dedicated his entire legal career to specialise in construction law. As a former Divisional President of the Master Builders Association NSW, he combines deep legal expertise with comprehensive industry knowledge. He maintains daily experience in building dispute tribunals (NCAT, VCAT, QCAT, TASCAT) and courts across multiple jurisdictions.
Unlike generalist lawyers who handle various legal matters, John specialises exclusively in construction law matters affecting homeowners, builders, contractors, and subcontractors. You receive focused expertise from a lawyer who understands both the legal framework and the practical realities of the building industry.
How Our Deadline Verification Service Works
Step 1: Book Your Free Consultation
Book your free consultation through our online calendar — choose a time that suits you. Schedule your no-obligation conversation via Calendly with immediate availability shown. There is no cost, no obligation, and no commitment required at this stage. This is your opportunity to discuss your specific payment claim deadline situation with John Dela Cruz, our Principal Lawyer.
Step 2: Discuss Your Matter with Our Principal Lawyer
Speak directly with John Dela Cruz, Principal Lawyer, about your payment claim and deadline situation. We will discuss your specific legal issue, and John may request additional documents (payment claim, contract, correspondence) to fully understand your situation and provide accurate deadline verification. This detailed conversation ensures we have all information necessary to calculate your deadline with complete certainty and assess your overall legal position.
Step 3: Receive Your Cost Disclosure & Proceed
We will provide a transparent cost disclosure outlining the scope of work required for your deadline verification and payment schedule preparation, along with associated fees. You will receive a clear breakdown of exactly what we will do and what it will cost. There are no hidden charges. You can review this information at your leisure and decide whether to proceed. The choice is entirely yours — there is no obligation to accept and proceed.
Frequently Asked Questions: 10-Business-Day Payment Schedule Deadlines NSW
Under the Security of Payment Act 1999 (NSW), a business day is any day other than Saturday, Sunday, or a gazetted NSW public holiday. This includes days such as Australia Day, Good Friday, Easter Monday, ANZAC Day, Queen's Birthday, Christmas Day, and Boxing Day. Banking holidays and local council holidays do not stop the deadline countdown — only nationally gazetted NSW public holidays are excluded from the 10-day count.
If you receive an email payment claim on Friday at any time, the service date is Friday. Your 10-business-day countdown begins on the next business day, which is Monday. This means your deadline starts counting from Monday, giving you 10 business days from that point (two calendar weeks plus potentially two additional days depending on public holidays).
No. The 10-business-day deadline under Section 14 of the Security of Payment Act 1999 (NSW) is absolute and cannot be extended under any circumstances, even with written agreement between you and the builder. This is a strict statutory requirement. Missing this deadline results in automatic loss of all defence rights, regardless of the reason for the delay. There are no exceptions.
If a payment claim is posted to you, it is deemed served on the seventh calendar day after the posting date, regardless of when it actually arrives. For example, a claim posted on 15 July is deemed served on 22 July (seven calendar days later). Your 10-business-day countdown begins on the next business day after 22 July, which would be 23 July (if 23 July is a business day). This rule applies regardless of whether you actually receive the letter.
Christmas Day (25 December) and Boxing Day (26 December) are excluded from the 10-business-day count as gazetted NSW public holidays. If your calculated deadline would fall on or cross these holidays, you must exclude these days from your count, which extends your actual deadline date. For example, a deadline that might otherwise fall on 24 December would be extended to 27 December (excluding 25-26 December and the following weekend). Use an NSW public holiday calendar to accurately identify all holidays affecting your deadline.
Missing the 10-business-day deadline has catastrophic consequences. You immediately lose all rights to dispute the payment claim on substantive grounds. The builder can recover the full claimed amount through adjudication or court proceedings without any defence from you. NCAT proceedings in this situation result in automatic orders for payment of the full claim amount, often with costs orders against you ($2,000–$8,000). There are no exceptions to this automatic liability — NCAT consistently rejects arguments for deadline extensions.
Professional deadline verification ($1,200–$3,500 investment) provides certainty and identifies potential errors before they cost you $50,000–$500,000+ in liability exposure. Deadline calculation appears simple but involves complex variables: service method interpretation, public holiday identification, business day counting, and verification of service date. If you're uncertain about any aspect — service method, service date, public holidays in your deadline window — professional verification is strongly recommended. Many homeowners incorrectly calculate deadlines by counting from receipt date rather than service date, losing 2–7 business days without realising it.
Get Expert Deadline Verification from a NSW Construction Law Specialist
Don't risk missing your critical 10-business-day payment schedule deadline. Get professional verification of your exact deadline date, ensuring compliance with NSW SOPA requirements and protecting your legal defence rights.
Your payment schedule deadline is absolute under NSW law. Missing it means automatic loss of all substantive defence rights and full liability for the payment claim amount — potentially $50,000–$500,000+ depending on your project.
Expert deadline verification ensures you know your exact deadline date with certainty. John Dela Cruz, Principal Lawyer with 17+ years of exclusive construction law experience, will review your payment claim, verify the service date and method, identify any public holidays affecting your deadline, and confirm your exact deadline date.
Your free first consultation includes discussion of your payment claim situation and assessment of your legal position. Following consultation, you will receive a transparent cost disclosure for deadline verification and payment schedule preparation services.