The final progress claim is the last payment request made by the builder under the NSW HIA Lump Sum Contract. It usually includes the remaining amount owing to the builder for the completed work, typically around 5% of the total contract price that has been retained throughout the project.
Homeowners need to ensure that they pay the final progress claim only after they are satisfied with the completed work and all contractual obligations have been met. The final payment should not be made until practical completion has been achieved, all defects have been rectified, and the occupation certificate (if required) has been issued.
If the builder does not receive the final payment when legitimately due, they may seek legal action and charge interest on the outstanding amount under the contract terms or pursue recovery through the Security of Payment Act 1999 (NSW). However, homeowners are entitled to withhold final payment if there are unresolved defects or incomplete work.
Additionally, the final progress claim should only be paid once the homeowner is satisfied with the completed work, as it is challenging to claim for defects or unfinished work once final payment has been made. Making final payment may be interpreted as acceptance of the work and can limit your rights to pursue defects claims later.
Homeowners should always ensure that the final payment is made only after receiving a final inspection report and a certificate of occupancy where applicable. It is also advisable to have a professional building inspector conduct a final inspection before releasing the final payment, as this provides independent verification of work quality and completion.
Before making final payment, homeowners should verify that all of the following have been completed: all building work is complete and complies with the contract, all defects identified during inspections have been rectified, the occupation certificate has been issued (if applicable), all warranties and maintenance manuals have been provided, and the builder has provided all statutory warranties required under NSW law. Final payment release triggers the start of warranty periods under the Home Building Compensation scheme and establishes practical completion for defects liability purposes.
Understanding the importance of the final progress claim and the conditions that should be met before payment protects homeowners from paying for incomplete or defective work.