SOPA Statement Requirements for Payment Claims
Understand the mandatory wording and compliance requirements for SOPA statements under NSW Section 13(9) to avoid claim invalidation.
You can be confident that you are getting the right legal advice.
This comprehensive guide explains everything NSW builders, contractors, and subcontractors need to know about SOPA statement requirements. You'll understand the exact wording mandated by law, placement requirements, consequences of non-compliance, and practical implementation guidance for valid NSW payment claims.
BOOK YOUR FREE FIRST CONSULTWhat Exact Wording is Required for SOPA Statements: The Complete Answer
The Short Answer
Under Section 13(9) of the Building and Construction Industry Security of Payment Act 1999 (NSW), every payment claim must include a statement that the claim is made in accordance with the Act. The statement must appear on the payment claim document itself and contain specific mandatory wording. NSW courts and adjudicators strictly enforce this requirement—claims lacking the mandatory statement are invalid and unenforceable, regardless of the legitimacy of the underlying work performed, and claimants lose access to the rapid 10-15 business day adjudication process entirely.
Understanding the Details
Section 13(9) of the Building and Construction Industry Security of Payment Act 1999 (NSW) requires that a payment claim include a statement to the effect that the claim is made in accordance with this Act—a mandatory requirement that adjudicators treat as a strict compliance obligation with no discretion to overlook omissions. This is not optional language—it is a mandatory statutory requirement that must appear on the face of the payment claim. The statement serves a critical legal purpose: it notifies the respondent (typically the head contractor or builder) that the claimant is exercising statutory rights under the Security of Payment Act and that a payment schedule response is required within 10 business days.
The specific wording commonly used in NSW practice is: "This payment claim is made in accordance with Section 13 of the Building and Construction Industry Security of Payment Act 1999."
However, the wording does not need to be verbatim. Courts have accepted variations such as "This is a payment claim under the Security of Payment Act 1999" or "This payment claim is made under the Building and Construction Industry Security of Payment Act 1999." The key is that the statement must clearly communicate that the claim is being made pursuant to the Act's statutory provisions.
For Home Building Act contracts (residential building work in NSW), the statement must also comply with any additional requirements specified in the contract or the Home Building Act 1989. Many residential building contracts incorporate additional payment claim notification requirements beyond the SOPA Act minimum.
The statement must appear on the payment claim document itself—email subject lines or cover letters are insufficient. Courts have held that placement outside the document creates invalidity even if the statement is technically present elsewhere, automatically disqualifying the claim from adjudication access. The claimant should place the statement on the first page, typically near the document heading or payment details section, to ensure the respondent has clear notice that statutory payment claim procedures are being invoked.
NSW Regulatory Framework
The Building and Construction Industry Security of Payment Act 1999 (NSW) provides statutory protection for payment claims in the construction industry. Section 13(9) is part of Section 13, which defines what constitutes a valid payment claim. This provision is not discretionary—it is a mandatory requirement for claim validity.
Under the Home Building Act 1989 (NSW), residential building contracts must comply with both the Security of Payment Act requirements and Home Building Act consumer protections. Section 13(9) compliance is a prerequisite for all payment claims, regardless of whether the work is residential or commercial.
NCAT (NSW Civil and Administrative Tribunal) Home Building Division cases have consistently held that payment claims lacking the Section 13(9) statement are invalid, with adjudicators refusing to determine claim merits and dismissing adjudication applications entirely under Section 17 of the Act. In several high-profile disputes, contractors have lost the right to payment because payment claims were served without the mandatory statement. The tribunal has refused to exercise discretion to overlook the requirement, treating it as a strict compliance obligation.
Real NSW Examples
Example 1: A residential builder on Sydney's North Shore submitted a progress payment claim for $180,000 worth of excavation and foundation work. The claim listed all the work completed, included detailed schedules and supporting documentation, and was otherwise properly formatted. However, the builder failed to include a Section 13(9) statement on the claim document itself. The head contractor rejected the claim on the grounds that it lacked statutory compliance. When the builder attempted to pursue adjudication, the adjudicator found the claim invalid and refused to determine its merits. The builder lost $180,000 in payment pending rectification and resubmission of the claim with the mandatory statement.
Example 2: A subcontractor electrician prepared a payment claim for $45,000 for electrical installation work on a commercial project in Brisbane. The claim included the Section 13(9) statement, but the wording simply stated "Payment claim under SPA" without reference to the Act itself. While the head contractor accepted and paid the claim without challenge, had a dispute arisen, this abbreviated wording might have been contested as non-compliant. Best practice requires full statutory reference to avoid future disputes.
Example 3: A commercial contractor submitted a progress payment claim for $520,000 for concrete works. The claim was technically compliant with all Section 13 requirements, including a proper Section 13(9) statement. The head contractor disputed the claim amount but paid a portion pending resolution. The contractor later pursued adjudication, where both parties' lawyers confirmed compliance with Section 13(9). The adjudication proceeded on the merits of the payment dispute, and the contractor recovered the withheld portion plus interest. Had the Section 13(9) statement been missing, the adjudication would have been dismissed before reaching the merits.
Detailed Analysis: SOPA Statement Requirements Under Section 13(9)
Statement Placement Within the Payment Claim
The Section 13(9) statement must appear on the payment claim document itself. This means the statement should be included in the body or footer of the claim—not merely in a cover email or accompanying letter. Courts have held that placement on the face of the claim is essential because it provides notice to the respondent of the statutory nature of the claim.
Best practice placement locations include:
- Immediately below the claim title or heading
- In a footer section of the claim document
- On the first page near the claim summary
- Preceding the payment schedule or invoice details
Mandatory Wording Elements
The Section 13(9) statement must contain the following mandatory elements:
- Explicit reference to the statutory framework: The statement must reference either "the Building and Construction Industry Security of Payment Act 1999" or "Section 13 of the [Act]" or simply "the Security of Payment Act 1999."
- Clear connection to the claim: The statement must link the claim to the statutory requirement—typically using language such as "This payment claim is made in accordance with..." or "This is a payment claim under..."
- Unambiguous statutory reference: Generic statements such as "This claim is made pursuant to applicable law" are insufficient.
Consequences of Non-Compliance
Missing or defective Section 13(9) statements have severe consequences for payment claims under NSW law, with adjudicators and courts applying strict compliance standards that cannot be waived:
- Claim Invalidity: A payment claim lacking the mandatory statement is invalid under the Act.
- Loss of Adjudication Rights: The claimant cannot pursue adjudication under Section 17 of the Act.
- Extended Dispute Resolution: Disputes must be resolved through more expensive and time-consuming methods.
- Financial Impact: Contractors and subcontractors lose the ability to recover payment quickly.
Integration with Other Section 13 Requirements
A valid payment claim must include multiple mandatory requirements beyond the statement in Section 13(9), including:
- Identification of the claimant
- Identification of the respondent
- Identification of the contract
- Description of work performed
- Claimed amount
- Due date for payment
- Supporting statement
Missing any single element can invalidate the entire claim.
Practical Application: Implementing SOPA Statement Compliance
Step-by-Step Implementation
- Draft the Statement: Select or draft appropriate statutory language. The standard formulation is: "This payment claim is made in accordance with Section 13 of the Building and Construction Industry Security of Payment Act 1999."
- Place on Claim Document: Insert the statement on the first page of the payment claim, immediately below the title or in a header section.
- Cross-Reference in Cover Letter: While not required, including a sentence in the cover letter referencing the statutory statement provides additional confirmation.
- Verify All Section 13 Elements: Before serving the claim, complete a checklist confirming all Section 13 requirements are met.
- Serve the Claim: Serve the completed payment claim on the respondent by the method specified in the contract. Retain proof of service.
- Document Compliance: Maintain records confirming that the Section 13(9) statement was included on the claim served.
Common Mistakes Avoiding Claim Invalidation
- Mistake 1: Omitting the Section 13(9) Statement Entirely.
- Mistake 2: Using Ambiguous or Non-Specific Wording.
- Mistake 3: Placing the Statement in a Cover Letter Rather Than on the Claim Document.
- Mistake 4: Including the Statement in Fine Print or Hidden Location.
- Mistake 5: Serving Claims Without Proof of Service.
- Mistake 6: Failing to Include Supporting Documentation under Section 13(3).
- Mistake 7: Allowing Contractual Amendment of Statutory Requirements.
When Professional Guidance is Essential
Professional legal guidance is essential in the following scenarios:
- High-Value Claims: For claims exceeding $100,000, professional review minimises invalidity risk.
- Disputed Claims: When a respondent disputes a claim or refuses to provide a payment schedule.
- Complex Projects: Multi-stage projects with numerous claims require systematic compliance management.
- Previous Claim Rejection: If a claim has been rejected for compliance reasons.
- Respondent Resistance: If the respondent challenges the validity of your Section 13(9) statement.
- Adjudication Pursuit: Expert legal representation significantly improves outcomes.
Real NSW Projects: SOPA Statement Compliance Outcomes
Case Study 1: Silent Statement Omission - $180,000 Claim Lost
A Sydney concrete contractor submitted a detailed $180,000 claim for foundation work. The problem? The claim was formatted as a professional invoice but lacked the mandatory Section 13(9) statement. The head contractor rejected it, and the subsequent adjudication application was immediately dismissed. The contractor was forced into negotiation, settling for $125,000—a loss of $55,000.
Key Lesson: Even well-documented claims fail if the Section 13(9) statement is missing. Its absence creates an invalidity that no amount of supporting documentation can cure.
Case Study 2: Proper Compliance - $520,000 Claim Successfully Recovered
A commercial subcontractor submitted a $520,000 claim with all Section 13 requirements met, including a prominent statement. The head contractor disputed the amount and reduced payment to $350,000. Because the claim was valid, the subcontractor could immediately pursue adjudication. The adjudicator ruled in their favor, ordering payment of $490,000 within 5 business days.
Key Lesson: Proper compliance unlocks rapid adjudication access where disputes are resolved on factual evidence, not procedural technicalities.
John Dela Cruz
Principal Lawyer, Contracts Specialist
Why Choose Contracts Specialist
When you work with Contracts Specialist, you receive legal advice directly from John Dela Cruz — Principal Lawyer with over 17 years of exclusive construction law experience.
John is an Australian Legal Practitioner and he services NSW, Queensland, Victoria, and Tasmania. He has dedicated his entire legal career to specialise in construction law. As a former Divisional President of the Master Builders Association NSW, he combines deep legal expertise with comprehensive industry knowledge. He maintains daily experience in building dispute tribunals (NCAT, VCAT, QCAT, TASCAT) and courts across multiple jurisdictions.
Unlike generalist lawyers who handle various legal matters, John specialises exclusively in construction law matters affecting homeowners, builders, contractors, and subcontractors. You receive focused expertise from a lawyer who understands both the legal framework and the practical realities of the building industry.
Frequently Asked Questions: SOPA Statements in NSW Payment Claims
The most commonly used statement is: "This payment claim is made in accordance with Section 13 of the Building and Construction Industry Security of Payment Act 1999." However, the wording does not need to be verbatim. Courts accept variations such as "This is a payment claim under the Security of Payment Act 1999" or "This payment claim is made in accordance with the Building and Construction Industry Security of Payment Act 1999." The key requirement is that the statement clearly references the Act and connects the claim to the statutory framework.
The statement must appear on the payment claim document itself—not in a cover email or accompanying letter. Best practice placement includes immediately below the claim title, in a header section, or in the footer area of the claim document where it is clearly visible. The statement should appear on the first page of the claim to ensure the respondent has immediate notice of its statutory nature.
A payment claim lacking a Section 13(9) statement is invalid under the Security of Payment Act. The respondent is not obligated to serve a payment schedule response, and the claimant loses access to adjudication. This can result in 2-6 month payment delays and force negotiations where the contractor typically recovers 10-20% less than the original claim amount. For claims exceeding $200,000, invalidity can represent hundreds of thousands of dollars in lost payment.
Contracts cannot eliminate or substantially modify the statutory Section 13(9) requirement—it is a mandatory provision of NSW law that cannot be contracted out of. However, contracts may impose additional requirements beyond the statutory minimum (e.g., specific recipients, particular service methods, or supporting documentation). For contracts that include Home Building Act provisions, you must comply with both the statutory SOPA requirement and any Home Building Act-specific payment notices.
This depends on how the respondent treats the resubmitted claim. If the resubmitted claim is treated as a new, separate claim, adjudication remains available. However, if it is treated as a duplicate submission or a revision of the original claim, disputes may arise about timing. Best practice is to include the statement on the original claim to avoid these complications. If you must resubmit, clearly indicate that you are providing a revised compliant claim and reference the original submission date.
Protect Your Payment Claims with Expert Compliance Review
SOPA statement compliance is not optional—it's essential for accessing payment recovery mechanisms like adjudication. Let a construction law specialist review your payment claim procedures to ensure comprehensive Section 13(9) compliance.