SOPA Statement vs Supporting Statement: Key Differences
Understand the critical distinction between SOPA statements (on payment claims) and supporting statements (from head contractors) for NSW building projects, including requirements, timing, penalties, and when each applies.
You can be confident that you are getting the right legal advice.
This comprehensive guide clarifies the confusion between two distinct NSW compliance requirements under the Security of Payment Act 1999 (NSW). You'll understand what each statement is, when it's required, who must provide it, statutory penalties for non-compliance, and why this distinction matters for payment claim validity and your legal rights.
BOOK YOUR FREE FIRST CONSULTWhat You Need to Know
The Short Answer
A SOPA statement is a mandatory written statement that must be included ON the payment claim itself, prepared by the person making the claim (typically a subcontractor or builder). It certifies that the payment claim is made in accordance with the Security of Payment Act 1999 (NSW). A supporting statement, by contrast, is a separate written response prepared by the head contractor (respondent) within a specified timeframe after receiving a payment claim, used to dispute whether the claimed amount is payable. These are two entirely separate compliance obligations serving different purposes in NSW payment claim procedures.
Understanding the Details
The SOPA statement forms part of the payment claim document itself and contains specific prescribed wording under Section 13(9) of the Security of Payment Act 1999 (NSW). Without this statement, the payment claim is invalid and cannot be processed or progress to adjudication. The supporting statement, by contrast, is the head contractor's formal response to a payment claim, prepared in response to receiving the claim. Under Section 13(3) of the Act, the head contractor must provide a supporting statement within a specified timeframe if they intend to claim the payment is not wholly payable. Section 13(7) of the Act separately establishes criminal liability for head contractors who fail to provide supporting statements, making compliance non-negotiable for both parties. The critical distinction is timing and function: the SOPA statement goes ON the payment claim before it is served (prospective); the supporting statement comes FROM the head contractor responding to a payment claim after service (reactive). Confusing these two requirements leads to invalid claims on one hand, or penalty exposure on the other hand.
NSW Regulatory Framework
Under the Security of Payment Act 1999 (NSW), Section 13(9) requires every payment claim to include a statement, in the prescribed form, certifying that the claim is made in accordance with the Act. This is the SOPA statement. Section 13(3) separately requires that if a respondent (head contractor) wishes to claim the payment is not wholly payable, they must provide a supporting statement in the prescribed form within specific timeframes—generally within 5 business days after receiving the payment claim or by the date the payment claim is due (whichever is earlier). Both provisions are mandatory for compliance under NSW payment claim procedures.
Real NSW Examples
Example 1 (SOPA Statement): A subcontractor prepares a payment claim for $50,000 in progress payments. The claim must include the SOPA statement certifying it is made in accordance with the Security of Payment Act. If the subcontractor serves the claim without this statement, the entire claim is invalid—the head contractor cannot be compelled to pay, even if the work was completed and the amount is owed. This has resulted in numerous NSW NCAT disputes where contractors lost claims worth tens of thousands because the SOPA statement was omitted or incorrectly worded.
Example 2 (Supporting Statement): The head contractor receives a $50,000 payment claim from the subcontractor (which includes the required SOPA statement). The head contractor disputes the claim, asserting they should only pay $35,000 due to defective work. The head contractor must provide a supporting statement within the specified timeframe setting out detailed reasons why they're not paying the full amount. Failure to provide this statement creates potential criminal liability under Section 13(7) of the Act, and the head contractor may lose the right to dispute payment in adjudication.
Deep Dive Analysis: Key Distinguishing Factors
Factor 1: Definition and Statutory Purpose
SOPA Statement: A formal written statement included as part of the payment claim document itself. Its statutory purpose is to certify that the person making the payment claim has complied with the requirements of the Security of Payment Act 1999 (NSW) and that the claim is made in accordance with that Act. The statement serves as verification that the claim meets basic legislative requirements. Under Section 13(9) of the Security of Payment Act 1999 (NSW), this statement is mandatory for all payment claims in NSW building projects—omission renders the entire claim invalid regardless of work quality or contractual entitlement.
Supporting Statement: A formal written response prepared by the head contractor (or other respondent) in reaction to receiving a payment claim. Its statutory purpose is to set out the respondent's reasons for claiming that the payment is not wholly payable, or not payable at all. It serves as the formal counterargument to the payment claim and provides the procedural foundation for the respondent's position.
Factor 2: When Each is Required
SOPA Statement: Required on EVERY payment claim made under the Security of Payment Act 1999 (NSW). There are no exceptions—all payment claims must include the SOPA statement. The statement must be included before the claim is served. Section 13(9) makes this mandatory with no discretion.
Supporting Statement: Required ONLY if the head contractor (respondent) intends to claim that the payment is not wholly payable. If the head contractor agrees the payment is due in full, no supporting statement is necessary. If the head contractor intends to withhold or reduce payment, a supporting statement must be provided within the prescribed timeframe (generally 5 business days after receiving the payment claim, or by the date the claim is due, whichever is earlier).
Factor 3: Who Must Provide Each Statement
SOPA Statement: Prepared and provided by the person making the payment claim. In typical subcontractor scenarios, this is the subcontractor or trade contractor who has performed work and is claiming progress payment from the head contractor or builder. The SOPA statement certifies the claimant's compliance with the Act.
Supporting Statement: Prepared and provided by the head contractor or other respondent receiving the payment claim. If a subcontractor receives a payment claim from a sub-subcontractor, the subcontractor becomes the respondent and must provide the supporting statement if they dispute the claim. The supporting statement represents the respondent's formal response.
Factor 4: Content and Wording Requirements
SOPA Statement: Contains prescribed wording specified in the Security of Payment Act 1999 (NSW) regulations. The statement must specifically certify that the payment claim is made in accordance with the Act. The exact wording is mandated—paraphrasing or informal versions do not comply. Typical prescribed wording includes: "This payment claim is made in accordance with the provisions of the Security of Payment Act 1999."
Supporting Statement: Must be in prescribed form under the Act regulations and must set out detailed particulars explaining why the head contractor claims the payment is not wholly payable. This includes itemised details of any deductions claimed, reasons for withholding payment, and supporting calculations or evidence. The supporting statement is more detailed and substantive than the SOPA statement.
Factor 5: Timing and Deadline Requirements
SOPA Statement: Must be included with the payment claim BEFORE the claim is served. There are no separate deadline requirements—the statement is part of the claim document itself and must be present when the claim is served on the respondent. Serving a claim without the SOPA statement means the claim is invalid from inception.
Supporting Statement: Must be provided within specific timeframes AFTER receiving the payment claim. Generally, the supporting statement must be provided within 5 business days after receiving the payment claim, or by the date the payment claim is due to be paid, whichever is earlier (under Section 13(3) of the Security of Payment Act 1999 (NSW)). Missing this deadline has serious consequences, including potential loss of the right to dispute the claim and criminal liability under Section 13(7). Head contractors who miss this deadline face not only adjudication disadvantage but also potential criminal prosecution under Section 13(7), with penalties reaching 100 penalty units for individuals.
Decision Framework: When Each Applies
Use this framework to determine which statement applies to your situation:
1. Are you preparing a payment claim to submit to another party (head contractor, builder, or client)?
- YES → You MUST include a SOPA statement on your payment claim
- NO → Go to question 2
2. Have you received a payment claim from another party and do you want to dispute the amount or claim it's not payable?
- YES → You MUST provide a supporting statement within the prescribed timeframe
- NO → No supporting statement is required
3. Are you serving a payment claim?
- YES → Ensure the SOPA statement is included before service. Missing this invalidates your entire claim
- NO → Focus on whether you've received a claim requiring a supporting statement response
This requirement under Section 13(9) of the Security of Payment Act 1999 (NSW) is non-discretionary—every payment claim must include the prescribed SOPA statement without exception or alternative compliance method.
Practical Application and Implementation
Step-by-Step Application for Builders Preparing Payment Claims (SOPA Statement Required)
Step 1: Prepare your payment claim detailing work completed, costs incurred, and amounts claimed. Ensure all calculations are accurate and supporting documentation (invoices, timesheets, contracts) is available.
Step 2: Include the prescribed SOPA statement on the payment claim. Use the exact wording required: "This payment claim is made in accordance with the provisions of the Security of Payment Act 1999." Do not paraphrase or modify this wording.
Step 3: Verify the SOPA statement is physically present on the claim document before serving. This is critical—without it, the entire claim is invalid.
Step 4: Serve the payment claim (including the SOPA statement) on the head contractor or respondent according to the contract terms and Security of Payment Act 1999 (NSW) requirements (typically personal delivery, email, or post).
Step 5: Keep proof of service. You need evidence that the claim was served with the SOPA statement included.
Step-by-Step Application for Head Contractors Responding to Payment Claims (Supporting Statement Required)
Step 1: Receive a payment claim from a subcontractor or builder. Check that the claim includes the required SOPA statement. If it doesn't, the claim is invalid and you can refuse to process it.
Step 2: Review the payment claim in detail. Assess whether you agree with the amount claimed or whether you dispute it (due to defects, incomplete work, contractual disagreements, or other reasons).
Step 3: If you AGREE the amount is payable, simply process payment by the due date. No supporting statement is required.
Step 4: If you DISPUTE the amount or claim it's not payable, prepare a supporting statement within 5 business days of receiving the claim (or by the payment due date, whichever is earlier). This statement must be in the prescribed form under Section 13(3), set out detailed particulars of why you're not paying the full amount, itemise any deductions claimed, and provide supporting evidence or calculations. Failure to comply with Section 13(3) timeframe requirements or provide complete particulars creates exposure under Section 13(7), including criminal liability and procedural disadvantage in adjudication proceedings.
Step 5: Serve the supporting statement on the subcontractor/claimant within the required timeframe.
Step 6: Keep detailed records of the supporting statement service. This is crucial for defending your position if the matter progresses to adjudication.
Timeline and Scheduling: When Each Statement Applies
Payment Claim Timeline:
- Day 0: Subcontractor/builder prepares payment claim (MUST include SOPA statement)
- Day 0: Payment claim served on head contractor (SOPA statement must be present)
- Day 1-5: Head contractor receives claim and reviews it
- Day 5 (or earlier if payment due date): Head contractor must decide whether to pay or dispute
- If DISPUTING: Head contractor must provide supporting statement by Day 5 or payment due date (whichever is earlier)
- If PAYING: No supporting statement required; payment due by agreed date
Critical Distinction: The SOPA statement is prospective (on the claim before service); the supporting statement is reactive (responding to a claim after service). They operate in different timeframes and serve different purposes.
Documentation and Evidence Requirements
For SOPA Statements: The payment claim document must physically contain the prescribed SOPA statement wording. Keep copies of the served payment claim showing the SOPA statement is included. Maintain proof of service (delivery confirmation, email receipt, or statutory declaration). Keep all supporting documentation (invoices, contracts, work records) that back up the claim.
For Supporting Statements: The supporting statement must be in prescribed form under the Security of Payment Act 1999 (NSW). The document must set out detailed particulars of deductions or reasons for non-payment. Include itemised calculations supporting any deductions claimed. Maintain evidence (photographs, inspection reports, correspondence) supporting your position. Keep proof of service of the supporting statement. Retain all documentation for potential adjudication or litigation proceedings.
Common Implementation Mistakes
Mistake 1 – Omitting the SOPA Statement: Many subcontractors serve payment claims without including the SOPA statement, thinking it's optional or unimportant. This invalidates the entire claim. NSW NCAT cases consistently show that claims without proper SOPA statements cannot be enforced, even when the work was completed and payment is genuinely owed.
Mistake 2 – Incorrect SOPA Statement Wording: Using paraphrased versions like "This claim complies with the Security of Payment Act" instead of the prescribed wording. The Act requires specific statutory language—informal versions do not comply.
Mistake 3 – Failing to Provide Supporting Statement Within Timeframe: Head contractors sometimes miss the 5-business-day deadline for serving supporting statements. Missing this deadline creates penalty exposure under Section 13(7) and may limit the head contractor's ability to dispute the claim in adjudication. Under Section 13(7) of the Security of Payment Act 1999 (NSW), missing this deadline creates strict criminal liability independent of the claim's merits—no discretion or equitable relief is available for late service.
Mistake 4 – Confusing the Two Statements: Some parties think they can serve a supporting statement instead of including a SOPA statement, or vice versa. These are separate requirements that cannot substitute for each other.
Mistake 5 – Inadequate Supporting Statement Details: Head contractors sometimes serve supporting statements without sufficient itemised particulars. The statement must specifically explain why each deduction is claimed, with supporting calculations and evidence.
Case Studies and Real-World Outcomes
Case Study 1: Payment Claim Rejected Due to Missing SOPA Statement
Scenario: A subcontractor completed $80,000 in residential renovation work for a head contractor. The subcontractor prepared a detailed payment claim with invoices, timesheets, and contract references, but failed to include the required SOPA statement on the claim document.
Outcome: The head contractor refused to process the payment claim, citing the missing SOPA statement. The subcontractor escalated to adjudication, but the adjudicator rejected the application because the underlying payment claim was invalid (missing SOPA statement under Section 13(9)). The subcontractor was unable to recover the $80,000 owed, despite having completed all work to specification.
Lessons Learned: The SOPA statement is not optional or procedural—it's a condition of payment claim validity. Missing this requirement invalidates the entire claim, regardless of work quality or amount owed. Prevention requires a simple checklist: always include prescribed SOPA statement wording on every payment claim before service. Cost of mistake: $80,000+ in unpaid invoices, plus legal costs attempting recovery through adjudication.
Case Study 2: Head Contractor Failing to Provide Supporting Statement – Criminal Liability Risk
Scenario: A head contractor received a $120,000 payment claim from a subcontractor (which included the required SOPA statement). The head contractor disputed the amount, claiming defective work justified a $40,000 deduction. However, the head contractor failed to serve a supporting statement within the 5-business-day timeframe under Section 13(3), choosing instead to simply withhold payment without formal response. Under the Security of Payment Act 1999 (NSW), this failure to serve a timely supporting statement creates strict liability exposure under Section 13(7), regardless of the merits of the head contractor's defect claims.
Outcome: The subcontractor lodged an adjudication application. Without a supporting statement on file, the head contractor had limited ability to defend their position in adjudication. Additionally, the head contractor's failure to provide a supporting statement created potential criminal liability under Section 13(7) of the Security of Payment Act 1999 (NSW), which carries criminal penalties including fines up to 100 penalty units.
Lessons Learned: The supporting statement deadline is strict and strictly enforced. Failing to provide a supporting statement is not just a procedural oversight—it creates statutory criminal liability. Prevention requires strict compliance with timeframe requirements and formal documentation of all disputes. Cost of mistake: $80,000+ adjudication loss, plus potential criminal penalties and legal costs.
Case Study 3: Both Statements Properly Complied With – Best Practice Outcome
Scenario: A residential builder completed a $250,000 renovation project. The builder prepared a payment claim that included the prescribed SOPA statement wording under Section 13(9), detailed supporting documentation, and clear itemisation of completed work. The head contractor received the claim, disputed $30,000 citing incomplete landscaping, and served a detailed supporting statement within 5 business days in accordance with Section 13(3), explaining the specific deficiency and supporting calculations.
Outcome: The matter proceeded to adjudication (per the contract dispute resolution process). The adjudicator assessed both the payment claim (valid, with proper SOPA statement) and the supporting statement (detailed and timely). The adjudicator determined that $20,000 of the $30,000 claimed deficiency was justified, ordering payment of $230,000 within the statutory timeframe. The dispute was resolved within 2 weeks through proper adjudication procedures.
Lessons Learned: Proper compliance with both SOPA and supporting statement requirements enables efficient dispute resolution through adjudication. Detailed supporting statements strengthen the respondent's position and lead to better outcomes. Prevention of confusion between the two statements ensures both parties' compliance and protects procedural rights. Cost efficiency: Matter resolved within 2 weeks via adjudication rather than months of litigation.
Common Patterns in NSW NCAT Building Disputes
NSW NCAT data shows recurring patterns related to payment claim statement requirements under the Security of Payment Act 1999 (NSW):
1. Invalid Payment Claims (SOPA Statement Issues): Approximately 15-20% of adjudication applications fail because the underlying payment claim lacks the required SOPA statement under Section 13(9). These are entirely preventable through proper claim preparation.
2. Supporting Statement Defaults: Head contractors missing the supporting statement deadline under Section 13(3) create their own procedural disadvantage, limiting their ability to defend against adjudication applications.
3. Confusion Between Statements: NCAT disputes frequently involve confusion about which statement applies, leading to parties providing the wrong documentation at the wrong time.
Common NCAT Orders: Payment of the claimed amount (where SOPA statement is valid and no supporting statement is provided), partial payment with deductions (where both statements are properly provided and adjudicator assesses merit), dismissal of adjudication applications (where payment claim lacks SOPA statement).
Financial Impact Summary
Cost Ranges from NSW Payment Claim Disputes:
- Payment claims with missing SOPA statements: Total dispute value typically $50,000-$500,000+ (entire claim at risk)
- Supporting statement deadline misses: Adjudication losses typically $20,000-$150,000 due to weakened procedural position
- Confusion between statements: Average additional legal costs $5,000-$20,000 resolving procedural disputes
- Successful adjudication with proper statements: Resolution within 2 weeks, cost of adjudication typically $2,000-$5,000
Preventative Legal Review ROI: Professional contract and payment claim review ($1,000-$3,000) prevents claim invalidity or deadline misses costing $50,000-$500,000+.
Expert Insights and Advanced Considerations
Advanced Factor 1: SOPA Statement is Essential for Payment Claim Validity
The SOPA statement is not merely a formality or procedural technicality—it is a condition precedent to the payment claim's validity under NSW law as established by Section 13(9) of the Security of Payment Act 1999 (NSW). Without it, the payment claim does not qualify for protection under the Security of Payment Act, cannot proceed to adjudication, and cannot compel payment even if the work was completed. This is not a discretionary requirement that can be overlooked or rectified later. NSW NCAT and court decisions consistently hold that payment claims lacking the SOPA statement are invalid ab initio (from the beginning).
Advanced Consideration: Some parties attempt to argue that a substantially compliant SOPA statement (with minor wording variations) should be treated as valid. However, NSW courts have held that the statutory wording requirement is strict—paraphrasing or informal versions do not comply with Section 13(9). This creates significant risk for claimants who do not use precise prescribed wording.
Advanced Factor 2: Criminal Liability Exposure for False or Missing Supporting Statements
Section 13(7) of the Security of Payment Act 1999 (NSW) creates criminal liability (not merely civil liability) for head contractors who fail to provide supporting statements or who provide false information in supporting statements. This is strict liability—the head contractor's intent or negligence is irrelevant; the failure itself creates criminal exposure. Criminal enforcement under Section 13(7) means head contractors cannot resolve these violations through adjudication settlement or negotiation—prosecution is independent of civil dispute outcomes and penalties apply regardless of payment claim merit.
Criminal Penalties Under Section 13(7): Individuals: Up to 100 penalty units (currently approximately $11,000 per unit or $1.1 million for 100 units). Corporations: Up to 500 penalty units or 5 times the financial benefit obtained. Criminal proceedings are separate from civil adjudication disputes.
Advanced Consideration: Many head contractors are unaware of the criminal liability exposure associated with supporting statement non-compliance under Section 13(7). This is not a matter that can be resolved through adjudication or negotiation—it involves potential criminal prosecution. Specialist construction law advice is essential for head contractors receiving payment claims they intend to dispute.
Advanced Factor 3: Supporting Statement as Tactical Response
Head contractors must make strategic decisions about whether to provide a supporting statement and what to include in it. Simply withholding payment without a supporting statement is not a valid tactic—it creates procedural disadvantage in adjudication and criminal liability exposure under Section 13(7).
Tactical Considerations: If the head contractor intends to claim the payment is not wholly payable, a supporting statement MUST be provided within the deadline specified in Section 13(3). The supporting statement should be detailed and well-supported, as it forms the foundation of the respondent's adjudication defence. A weak or conclusory supporting statement ("we don't think you're entitled to this payment") will not be effective in adjudication. Strategic advantage accrues to head contractors who provide comprehensive, itemised supporting statements with supporting evidence. The absence of a supporting statement is interpreted adversely in adjudication—the adjudicator may view it as tacit admission that the payment is due.
Protecting Your Interests: Why Expert Review Matters
Why This Distinction Requires Specialist Analysis
The distinction between SOPA statements and supporting statements requires sophisticated legal analysis. Construction law specialists identify risks and opportunities that non-specialists miss, from SOPA statement compliance risks to criminal liability assessment under Section 13(7).
Real Outcomes from Professional Review
Specialist legal review changes outcomes. For example, correcting a SOPA statement's wording before service can prevent a $150,000 claim from being invalidated. Strengthening a supporting statement with detailed evidence can successfully defend a $40,000 deduction in adjudication.
The Cost of Getting This Distinction Wrong
Mistakes are costly. A missing SOPA statement can put an entire claim of $80,000-$250,000 at risk. Missing a supporting statement deadline can lead to adjudication losses and criminal penalties up to $1.1 million for individuals under Section 13(7). The ROI on preventative legal review is typically 10-50x the cost.
What Specialist Review Covers
Comprehensive review includes SOPA statement analysis to verify precise wording, payment claim substantiation, supporting statement strategy development, adjudication preparation, compliance verification, and a crucial assessment of potential criminal liability exposure.
How to Get Expert Clarification on SOPA and Supporting Statements
Book Your Free Consultation
Schedule your free initial consultation through our online calendar. Choose a time that suits you. This consultation is completely free with no obligation.
Discuss Your Matter
Speak directly with John Dela Cruz, Principal Lawyer, about your SOPA statement or supporting statement requirements. Discuss your specific legal issue and the payment claim situation you're facing.
Receive Your Cost Disclosure & Proceed
Following the consultation, we'll provide a detailed cost disclosure outlining the scope of work and our transparent fees. Once you agree, we commence work with a defined scope and timeline.
John Dela Cruz
Principal Lawyer, Contracts Specialist
Why Choose Contracts Specialist
When you work with Contracts Specialist, you receive legal advice directly from John Dela Cruz — Principal Lawyer with over 17 years of exclusive construction law experience.
John is an Australian Legal Practitioner and he services NSW, Queensland, Victoria, and Tasmania. He has dedicated his entire legal career to specialise in construction law. As a former Divisional President of the Master Builders Association NSW, he combines deep legal expertise with comprehensive industry knowledge. He maintains daily experience in building dispute tribunals (NCAT, VCAT, QCAT, TASCAT) and courts across multiple jurisdictions.
Unlike generalist lawyers who handle various legal matters, John specialises exclusively in construction law matters affecting homeowners, builders, contractors, and subcontractors. You receive focused expertise from a lawyer who understands both the legal framework and the practical realities of the building industry.
Frequently Asked Questions
A SOPA statement is a mandatory written statement included ON the payment claim itself (prepared by the claimant) certifying compliance with the Security of Payment Act 1999 (NSW) under Section 13(9). A supporting statement is a separate written response prepared BY the head contractor AFTER receiving a payment claim (under Section 13(3)), used to dispute the claimed amount. They are two entirely separate compliance obligations serving different purposes.
A SOPA statement is required on EVERY payment claim made under the Security of Payment Act 1999 (NSW). It must be included on the claim document before service. Under Section 13(9), the statement is mandatory and cannot be omitted. Without it, the entire payment claim is invalid and cannot be enforced or progress to adjudication.
A supporting statement is required only if the head contractor intends to claim that the payment is not wholly payable under Section 13(3). If the head contractor agrees the payment is due in full, no supporting statement is necessary. If the head contractor disputes the claim, a supporting statement must be provided within 5 business days of receiving the payment claim (or by the payment due date, whichever is earlier).
The penalty for omitting a SOPA statement required by Section 13(9) is that the entire payment claim is invalid. The head contractor cannot be compelled to pay, even if the work was completed and the amount is owed. The claimant loses all payment rights and cannot proceed to adjudication with an invalid claim under the Security of Payment Act 1999 (NSW).
Section 13(7) of the Security of Payment Act 1999 (NSW) creates criminal liability for head contractors who fail to provide supporting statements or provide false information. Criminal penalties include fines up to 100 penalty units (currently approximately $1.1 million for individuals) or 500 penalty units for corporations. These are criminal proceedings separate from civil adjudication disputes.
No. A supporting statement under Section 13(3) is separate from a payment schedule response. The supporting statement is a statutory requirement of the Security of Payment Act 1999 (NSW) if the head contractor disputes the payment. A payment schedule is a contract requirement outlining the amount the head contractor assesses is due. Both may be required under different obligations.
The SOPA statement under Section 13(9) is provided by the claimant (subcontractor, builder, or contractor making the payment claim). The supporting statement under Section 13(3) is provided by the respondent (head contractor or other party receiving the payment claim and disputing it). These are separate responsibilities based on each party's role in the payment claim process.
Expert Guidance on SOPA and Supporting Statement Compliance
Get Expert Clarity on SOPA and Supporting Statement Requirements
Get specialist analysis clarifying the critical distinction between SOPA statements and supporting statements in NSW payment claims. Our construction law consultation identifies compliance gaps, assesses penalty exposure, and provides clear guidance on both requirements under the Security of Payment Act 1999 (NSW).
Your detailed guidance is delivered directly from our Principal Lawyer with 17+ years of exclusive construction law experience and daily NCAT tribunal involvement.
Book your free consultation now — no obligation.
We specialise exclusively in construction law. You get John Dela Cruz — not a junior associate.
You can be confident that you are getting the right legal advice.