Construction Lawyer & Building Solicitors Sydney | Contracts Specialist Law Firm

Payment Claims Under the Security of Payment Act NSW | Contracts Specialist

Payment Claims Under the
Security of Payment Act

Recover unpaid progress payments by serving a valid payment claim under NSW's Security of Payment Act.

You can be confident that you are getting the right legal advice.

The Building and Construction Industry Security of Payment Act 1999 (NSW) enables contractors, subcontractors, and suppliers to recover progress payments through the simple act of serving a payment claim. Understanding what makes a payment claim valid and how to serve it correctly is essential to protecting your right to payment.

Book Your Free First Consult

What is a Payment Claim?

A payment claim is a formal document that you serve on the person owing you money (the respondent) to enforce your right to collect progress payments for construction work performed, related services rendered, or goods supplied.

Under the Security of Payment Act, a payment claim is more than just an invoice. It's a statutory document that triggers specific legal timeframes and obligations. Once you serve a valid payment claim, the respondent has a limited time to respond with a payment schedule. If they fail to respond, you can suspend work or pursue rapid adjudication to recover your money.

The payment claim mechanism was specifically designed to address cash flow problems in the construction industry. It provides contractors and subcontractors with a fast-track process to recover payments without lengthy court proceedings. This makes understanding payment claims essential for anyone working in construction.

What Makes a Payment Claim Valid?

There's not one single payment claim form you need to adhere to. What matters is the content. To be valid under the Security of Payment Act, your payment claim must contain specific mandatory elements.

The three essential requirements are non-negotiable. Without them, your payment claim would be unenforceable, meaning you cannot pursue adjudication or other remedies under the Act.

1. Description of Works, Goods, or Services

Your payment claim must include a description of the construction work performed, goods supplied, or services rendered. This description should be sufficiently detailed to allow the respondent to understand what they're being charged for.

The level of detail required depends on your contract and the circumstances. For simple projects, a brief description may suffice. For complex projects, you may need to provide detailed breakdowns, reference specific contract clauses, or attach supporting documentation.

The key principle is that the respondent should be able to identify what work or materials correspond to the claimed amount. Vague descriptions like 'construction work' without further detail may render your payment claim invalid.

2. The Claimed Amount

You must clearly state the amount of money you're claiming. This should be expressed as a specific dollar figure, not a range or estimate.

The claimed amount can include:

  • The value of work completed or goods supplied
  • Retention money that has become due
  • Variations that have been performed
  • Any other amounts payable under the contract

You can claim GST as part of your payment claim if you're registered for GST. Make sure to state whether your claimed amount includes or excludes GST to avoid confusion.

3. Statement that Claim is Made Under the Act

Your payment claim must state that it is made pursuant to the Building and Construction Industry Security of Payment Act 1999 (NSW). This is a mandatory requirement that clearly identifies your document as a statutory payment claim.

Common ways to satisfy this requirement include:

  • 'This payment claim is made under the Building and Construction Industry Security of Payment Act 1999 (NSW)'
  • 'Payment claim pursuant to the Security of Payment Act'
  • 'This is a payment claim under the SOP Act'

Without this statement, your document may be treated as an ordinary invoice rather than a statutory payment claim, which means you lose the protections and remedies available under the Act.

1. Description of Works, Goods, or Services

Your payment claim must include a description of the construction work performed, goods supplied, or services rendered. This description should be sufficiently detailed to allow the respondent to understand what they're being charged for.

The level of detail required depends on your contract and the circumstances. For simple projects, a brief description may suffice. For complex projects, you may need to provide detailed breakdowns, reference specific contract clauses, or attach supporting documentation.

The key principle is that the respondent should be able to identify what work or materials correspond to the claimed amount. Vague descriptions like 'construction work' without further detail may render your payment claim invalid.

2. The Claimed Amount

You must clearly state the amount of money you're claiming. This should be expressed as a specific dollar figure, not a range or estimate.

The claimed amount can include:

  • The value of work completed or goods supplied
  • Retention money that has become due
  • Variations that have been performed
  • Any other amounts payable under the contract

You can claim GST as part of your payment claim if you're registered for GST. Make sure to state whether your claimed amount includes or excludes GST to avoid confusion.

3. Statement that Claim is Made Under the Act

Your payment claim must state that it is made pursuant to the Building and Construction Industry Security of Payment Act 1999 (NSW). This is a mandatory requirement that clearly identifies your document as a statutory payment claim.

Common ways to satisfy this requirement include:

  • 'This payment claim is made under the Building and Construction Industry Security of Payment Act 1999 (NSW)'
  • 'Payment claim pursuant to the Security of Payment Act'
  • 'This is a payment claim under the SOP Act'

Without this statement, your document may be treated as an ordinary invoice rather than a statutory payment claim, which means you lose the protections and remedies available under the Act.

→ Swipe to see all requirements

SOPA Payment Claim Checklist - Essential Requirements for Valid Payment Claims Under Security of Payment Act NSW

Quick reference checklist for preparing valid payment claims under the Security of Payment Act

For more information about the difference between a SOPA statement and supporting statement, see our detailed guide.

Payment Claim Timing:
When Can You Serve a Claim?

Understanding when you can serve a payment claim is critical to protecting your rights under the Security of Payment Act. The Act establishes specific timing rules based on "named months" that determine when payment claims can be served.

When Can You Serve a Payment Claim?

Under Section 13 of the Security of Payment Act, a payment claim may be served:

  • On and from the last day of the named month in which the construction work was first carried out (or the related goods and services were first supplied) under the contract, and on and from the last day of each subsequent named month.
  • OR, if the construction contract specifies an earlier date for serving a payment claim in any particular named month, the claim may be served on and from that earlier date instead of the last day of that month.
  • In the case of a terminated contract, a payment claim may be served on and from the date of termination.

Example

If construction work first commenced on 15 March 2024, you can serve a payment claim:

  • • On or after 31 March 2024 (last day of March - the named month work commenced)
  • • On or after 30 April 2024 (last day of April - subsequent named month)
  • • On or after 31 May 2024 (last day of May - subsequent named month)
  • • And so on for each subsequent month

However, if your contract states "payment claims must be served by the 20th of each month," then you can serve claims on or after the 20th of each month instead of waiting until the last day of the month.

Critical Rules About Payment Claim Timing

One Claim Per Named Month Rule: You can only serve one payment claim in any particular named month for construction work carried out or undertaken to be carried out (or for related goods and services supplied or undertaken to be supplied) in that month.

This means you cannot serve multiple payment claims for work done in the same named month. However, Section 13(6) allows you to:

  • • Serve a single payment claim in respect of more than one progress payment
  • • Include in a payment claim an amount that has been the subject of a previous claim
  • • Serve a payment claim in a particular named month for construction work carried out in a previous named month

This allows you to progressively claim unpaid amounts from previous months without being restricted to one claim per contract.

12-Month Time Limit: A payment claim may only be served within 12 months after the construction work to which the claim relates was last carried out (or the related goods and services were last supplied), or the period determined by your construction contract, whichever is later (Section 13(4)).

How Do I Validly Serve
a Payment Claim?

Once your payment claim is completed with all the necessary details, it must be served on the respondent (the person who owes you money) at their ordinary place of business. Service means delivering the payment claim in a way that's legally recognised under the Act.

The method of service is important because it affects when the payment claim is considered 'served' and when the respondent's time to respond begins. The Security of Payment Act allows several service methods:

Personal Service

Personally handing the payment claim directly to the respondent or their authorised representative. This is the most certain method of service as you have direct confirmation of delivery. Obtain a signature or written acknowledgment if possible.

Courier Service

Using a courier service to deliver the payment claim to the respondent's ordinary place of business. Keep your courier receipt and tracking information as proof of delivery. The payment claim is served when the courier delivers it.

Postal Service

Sending the payment claim by express post, registered post, or ordinary post to the respondent's ordinary place of business. Service by post is effective when the payment claim would be delivered in the ordinary course of post, not when you post it.

Facsimile (If Agreed)

Sending the payment claim by fax, but only if this method is agreed to in your contract. Keep the successful transmission confirmation. Not commonly used today due to email being more reliable.

Email Service

Sending the payment claim to an email address provided by the respondent for service of documents. This has become the most common method. Keep the sent email confirmation and consider requesting a read receipt for additional proof.

Contractual Methods

Using any other means of service agreed upon in your contract. Always check your contract for specific service requirements or preferred methods. Some contracts specify particular email addresses or procedures for payment claims.

Personal Service

Personally handing the payment claim directly to the respondent or their authorised representative. This is the most certain method of service as you have direct confirmation of delivery. Obtain a signature or written acknowledgment if possible.

Courier Service

Using a courier service to deliver the payment claim to the respondent's ordinary place of business. Keep your courier receipt and tracking information as proof of delivery. The payment claim is served when the courier delivers it.

Postal Service

Sending the payment claim by express post, registered post, or ordinary post to the respondent's ordinary place of business. Service by post is effective when the payment claim would be delivered in the ordinary course of post, not when you post it.

Facsimile (If Agreed)

Sending the payment claim by fax, but only if this method is agreed to in your contract. Keep the successful transmission confirmation. Not commonly used today due to email being more reliable.

Email Service

Sending the payment claim to an email address provided by the respondent for service of documents. This has become the most common method. Keep the sent email confirmation and consider requesting a read receipt for additional proof.

Contractual Methods

Using any other means of service agreed upon in your contract. Always check your contract for specific service requirements or preferred methods. Some contracts specify particular email addresses or procedures for payment claims.

→ Swipe to see all service methods

Always keep detailed records of how and when you served your payment claim. This evidence becomes critical if you need to pursue adjudication or if there's any dispute about whether the payment claim was validly served.

For more information about Security of Payment NSW invoice requirements, see our detailed guide.

Payment Claim Timeline and
What Happens Next

Understanding the timeline after serving a payment claim is crucial to protecting your payment rights. The Security of Payment Act creates strict timeframes that both you and the respondent must follow.

Payment Claim Process Under Security of Payment Act NSW - Complete Timeline Flowchart

Visual guide to the complete payment claim process under the Security of Payment Act NSW

Respondent's Payment Schedule Deadline

After you serve a payment claim, the respondent has a limited time to respond with a payment schedule. The deadline is either:

  • The time specified in your contract for providing a payment schedule, or
  • 10 business days after the payment claim is served (if your contract doesn't specify a time)

The payment schedule must identify the payment claim, indicate the amount the respondent proposes to pay, and if less than the claimed amount, provide reasons why. If the respondent fails to provide a payment schedule by the deadline, significant consequences follow.

When is Payment Actually Due?

Under Section 11 of the Security of Payment Act, the due date for payment depends on who you are claiming from:

  • Principal to Head Contractor: 15 business days after a payment claim is made (or an earlier date as provided in the contract terms)
  • To Subcontractors: 20 business days after a payment claim is made (or an earlier date as provided in the contract terms)
  • Exempt Residential Contracts: The date specified in the contract, or 10 business days after a payment claim is made if the contract doesn't specify

Important: These are the maximum payment timeframes. Contracts cannot extend these periods - any provision allowing later payment has no effect (Section 11(8)).

Consequences of No Payment Schedule

If the respondent doesn't provide a payment schedule within the required timeframe, they become liable to pay you the full claimed amount. At this point, you have several options:

  • Suspend work under the contract until payment is made
  • Commence debt recovery proceedings to recover the amount as a debt
  • Apply to have the payment claim adjudicated

These remedies are powerful tools to ensure you get paid. However, you must follow the correct procedures to access them.

If You Receive a Payment Schedule

If the respondent provides a payment schedule proposing to pay less than your claimed amount, you can apply for adjudication. You must lodge your adjudication application within 10 business days after receiving the payment schedule, or within 5 business days after the scheduled payment date, whichever is later.

Adjudication provides a rapid determination of your payment dispute, typically within 15-20 business days. An independent adjudicator reviews the payment claim, payment schedule, and submissions from both parties before making a binding decision.

For a visual representation of the complete process, see our Security of Payment NSW flowchart.

Common Payment Claim
Mistakes to Avoid

Many payment claims fail not because they lack merit, but because they contain technical defects that render them invalid. Avoiding these common mistakes can mean the difference between getting paid and losing your payment rights.

Incorrect Timing for Serving

Serving a payment claim before the correct date (on and from the last day of the named month, or an earlier date specified in your contract) can invalidate your claim. Ensure you serve on or after the permitted date under Section 13.

Insufficient Description

Providing vague or inadequate descriptions of the work, goods, or services makes your payment claim vulnerable to challenge. Be specific enough that the respondent can identify what they're being charged for.

Missing SOPA Statement

Forgetting to include the statement that your claim is made under the Security of Payment Act is a critical error. This statement is mandatory and without it, your document is just an invoice, not a payment claim.

Multiple Claims per Named Month

You can only serve one payment claim in any particular named month for work done in that month. Serving multiple claims for the same named month invalidates subsequent claims. However, you can include previously unpaid amounts in later claims for different months.

Incorrect Service Method

Using a service method not permitted by your contract or the Act can render service invalid. Always check your contract for specified service methods and keep proof of service documentation.

Serving Too Early

Serving a payment claim before the permitted date makes the claim invalid. You can only serve on and from the last day of the named month (or an earlier date if specified in your contract for that month).

Incorrect Timing for Serving

Serving a payment claim before the correct date (on and from the last day of the named month, or an earlier date specified in your contract) can invalidate your claim. Ensure you serve on or after the permitted date under Section 13.

Insufficient Description

Providing vague or inadequate descriptions of the work, goods, or services makes your payment claim vulnerable to challenge. Be specific enough that the respondent can identify what they're being charged for.

Missing SOPA Statement

Forgetting to include the statement that your claim is made under the Security of Payment Act is a critical error. This statement is mandatory and without it, your document is just an invoice, not a payment claim.

Multiple Claims per Named Month

You can only serve one payment claim in any particular named month for work done in that month. Serving multiple claims for the same named month invalidates subsequent claims. However, you can include previously unpaid amounts in later claims for different months.

Incorrect Service Method

Using a service method not permitted by your contract or the Act can render service invalid. Always check your contract for specified service methods and keep proof of service documentation.

Serving Too Early

Serving a payment claim before the permitted date makes the claim invalid. You can only serve on and from the last day of the named month (or an earlier date if specified in your contract for that month).

→ Swipe to see all common mistakes

Preparing and serving a valid payment claim requires careful attention to technical requirements and strict deadlines. Small errors can have significant consequences, potentially preventing you from recovering money you're legitimately owed. If you're dealing with a payment claim situation—whether preparing your first claim, responding to a claim, or pursuing adjudication—specialist construction law advice can help you navigate the process correctly and protect your payment rights. John Dela Cruz provides practical guidance on Security of Payment Act compliance and debt recovery strategies for contractors, subcontractors, and suppliers throughout NSW.

Why Choose Contracts Specialist

John Dela Cruz - Principal Lawyer, Contracts Specialist

John Dela Cruz
Principal Lawyer, Contracts Specialist

When you work with Contracts Specialist, you receive legal advice directly from John Dela Cruz — Principal Lawyer with over 17 years of exclusive construction law experience.

John is an Australian Legal Practitioner and he services NSW, Queensland, Victoria, and Tasmania. He has dedicated his entire legal career to specialise in construction law. As a former Divisional President of the Master Builders Association NSW, he combines deep legal expertise with comprehensive industry knowledge. He maintains daily experience in building dispute tribunals (NCAT, VCAT, QCAT, TASCAT) and courts across multiple jurisdictions.

Unlike generalist lawyers who handle various legal matters, John specialises exclusively in construction law matters affecting homeowners, builders, contractors, and subcontractors. You receive focused expertise from a lawyer who understands both the legal framework and the practical realities of the building industry.

How to Get Started

1

Book Your Free Consultation

Book your free consultation through our online calendar - choose a time that suits you. No cost, no obligation. You'll have direct access to our Principal Lawyer to discuss your payment claim matter.

2

Discuss Your Matter with Our Principal Lawyer

Speak directly with John Dela Cruz, Principal Lawyer, about your construction law matter. We may request additional documents such as your contract, correspondence, and payment records to fully understand your situation and provide accurate advice.

3

Receive Your Cost Disclosure & Proceed

Receive a detailed cost disclosure outlining the scope of work and fees for your matter. Review the proposal and agree to proceed when you're ready. We provide transparent fixed fees with no hidden costs, so you know exactly what to expect.

Get Specialist Advice on Payment Claims and Security of Payment

Whether you're preparing your first payment claim, responding to a claim served on you, or pursuing adjudication for unpaid amounts, our Principal Lawyer provides specialist construction law guidance with transparent fees and direct access.

Protect your payment rights under the Security of Payment Act. Book your free consultation today - understand your legal position with no cost and no obligation.

Frequently Asked Questions
About Payment Claims

Can I serve a payment claim if I don't have a written contract?

Yes. The Security of Payment Act applies even if you don't have a written contract. You can still serve a payment claim for construction work, goods supplied, or services rendered. However, without a written contract specifying an earlier date for serving payment claims, you can serve claims on and from the last day of each named month.

What's the difference between a payment claim and a regular invoice?

A payment claim is a statutory document served under the Security of Payment Act that triggers specific legal timeframes and obligations. A regular invoice is simply a request for payment without statutory backing. A payment claim must state it's made under the Act and, if valid, gives you access to rapid adjudication and other remedies if you're not paid.

How long does the respondent have to pay after I serve a payment claim?

Under the Security of Payment Act, the due date for payment depends on who you are claiming from: principals must pay head contractors within 15 business days after a payment claim is made, while payments to subcontractors are due within 20 business days. For exempt residential contracts, payment is due as specified in the contract, or 10 business days if not specified. Your contract may specify earlier payment dates, but cannot extend these maximum periods. The respondent must either pay the claimed amount or provide a payment schedule within 10 business days of receiving your claim.

What happens if I make a mistake in my payment claim?

The consequences depend on the type of mistake. Minor errors in descriptions or calculations may not invalidate your claim, but missing mandatory elements (claimed amount, description, SOPA statement) will render it invalid. If you discover a significant error, you may need to serve a new payment claim for a subsequent named month, as you cannot serve multiple claims for the same named month for work done in that month.

Can I include retention money in my payment claim?

Yes, you can claim retention money that has become due and payable under your contract. This typically occurs upon practical completion or after the defects liability period expires, depending on your contract terms. Include the retention amount in your claimed amount and ensure your description identifies that you're claiming retention money.

Do I need a lawyer to prepare a payment claim?

While you're not legally required to use a lawyer to prepare a payment claim, getting it wrong can have serious consequences. Invalid payment claims prevent you from accessing the Security of Payment Act's remedies. Many contractors and subcontractors benefit from legal advice, particularly for large claims, complex projects, or situations involving previous disputes with the respondent.

Can I serve a payment claim for work done months ago?

Yes, but there are practical and legal limitations. Payment claims may only be served within 12 months after the construction work was last carried out (or the period determined by your contract, whichever is later). You can serve a payment claim in any named month for construction work carried out in a previous named month, though waiting too long may create evidential difficulties and could affect your ability to prove the work was done and its value.

Can I serve a payment claim if I don't have a written contract?

Yes. The Security of Payment Act applies even if you don't have a written contract. You can still serve a payment claim for construction work, goods supplied, or services rendered. However, without a written contract specifying an earlier date for serving payment claims, you can serve claims on and from the last day of each named month.

What's the difference between a payment claim and a regular invoice?

A payment claim is a statutory document served under the Security of Payment Act that triggers specific legal timeframes and obligations. A regular invoice is simply a request for payment without statutory backing.

How long does the respondent have to pay after I serve a payment claim?

Under the Security of Payment Act, principals must pay head contractors within 15 business days, while payments to subcontractors are due within 20 business days. Exempt residential contracts follow contract terms or 10 business days if not specified. The respondent must provide a payment schedule within 10 business days if disputing your claim.

What happens if I make a mistake in my payment claim?

The consequences depend on the type of mistake. Minor errors may not invalidate your claim, but missing mandatory elements will render it invalid. You may need to serve a new payment claim for a subsequent named month.

Can I include retention money in my payment claim?

Yes, you can claim retention money that has become due and payable under your contract. This typically occurs upon practical completion or after the defects liability period expires. Include the retention amount in your claimed amount.

Do I need a lawyer to prepare a payment claim?

While not legally required, getting it wrong can have serious consequences. Invalid payment claims prevent you from accessing the Security of Payment Act's remedies. Many benefit from legal advice for large claims or complex projects.

Can I serve a payment claim for work done months ago?

Yes, but payment claims may only be served within 12 months after the work was last carried out (or the period determined by your contract, whichever is later). You can serve a claim in any named month for work done in a previous month. Waiting too long may create evidential difficulties.

→ Swipe to see all FAQs

Related Resources

Security of Payment Act NSW: Complete Guide

Comprehensive overview of the Security of Payment Act, including eligibility, processes, and your rights as a claimant or respondent.

Learn More →

SOPA Statement vs Supporting Statement

Understand the critical differences between a SOPA statement and supporting statement in payment claims and adjudication applications.

Learn More →

Security of Payment NSW Invoice Requirements

Learn what information your invoices must contain to comply with Security of Payment Act requirements.

Learn More →

Security of Payment NSW Flowchart Guide

Visual guide to the complete Security of Payment process, from serving a payment claim through to adjudication.

Learn More →

Security of Payment Act NSW: Complete Guide

Comprehensive overview of the Security of Payment Act, including eligibility, processes, and your rights as a claimant or respondent.

Learn More →

SOPA Statement vs Supporting Statement

Understand the critical differences between a SOPA statement and supporting statement in payment claims and adjudication applications.

Learn More →

Security of Payment NSW Invoice Requirements

Learn what information your invoices must contain to comply with Security of Payment Act requirements.

Learn More →

Security of Payment NSW Flowchart Guide

Visual guide to the complete Security of Payment process, from serving a payment claim through to adjudication.

Learn More →

→ Swipe to see all resources

Payment Claim: Enforce Your Right to Recover Payment Under the Security of Payment Act
Fill Out the Form to Download
Payment Claim: Enforce Your Right to Recover Payment Under the Security of Payment Act
The Complete Handbook for Homeowners: Navigating Construction Law in New South Wales

If you’re a homeowner in New South Wales, it’s crucial to understand Construction Law to protect your investment. This ultimate guide to Construction Law is specifically designed to provide homeowners with essential insights into the legal landscape of home building in NSW.

The Complete Handbook for Homeowners: Navigating Construction Law in New South Wales

If you’re a homeowner in New South Wales, it’s crucial to understand Construction Law to protect your investment. This ultimate guide to Construction Law is specifically designed to provide homeowners with essential insights into the legal landscape of home building in NSW.