Learn how the Dyjecinska case clarified whether homeowners must pay builders when the residential building contract was never signed.
You can be confident that you are getting the right legal advice.
Dyjecinska v Step-Up Renovations (NSW) Pty Ltd [2024] NSWSC 159 ('the Dyjecinska case') provides critical guidance for NSW homeowners facing building disputes where contracts remain unsigned. This matter — culminating in a NSW Supreme Court decision in February 2024 that affirmed the NCAT Appeal Panel — examined whether an unsigned MBA BC4 contract could be enforced under the Home Building Act 1989 (NSW), establishing important precedent about contract enforceability and payment obligations.
BOOK YOUR FIRST FREE CONSULTIn the Dyjecinska case, the homeowner, Isabela Dyjecinska, entered into an agreement with the builder, Step Up Renovations (NSW) Pty Ltd. The agreement was a NSW construction contract for alterations and additions. The parties used a Master Builders Association of NSW Residential Building BC4 Contract, commonly known as the MBA BC4 contract.
However, the contract was not signed by either party.
One of the main issues in the dispute was whether the builder could enforce the unsigned contract. The homeowner argued that the builder was in breach of the Home Building Act 1989 1989 (NSW) sections 7(1) and 7B — the former because the contract failed to meet the statutory requirements for residential building contracts, and the latter because the builder failed to provide the homeowner with a signed copy of the contract within five clear business days of entry. The Owner's position was that both contraventions rendered the contract unenforceable against the builder under section 10(1) of the Home Building Act.
This case highlights a critical issue for NSW homeowners: understanding when an unsigned building contract can still create legally binding obligations. The Home Building Act establishes specific requirements for residential building contracts to protect consumers, but the absence of signatures doesn't automatically render a contract void.
Understanding your payment obligations under an unsigned contract is essential before allowing any residential building work to commence on your property.
The Appeal Panel allowed the homeowner's appeal in part, but not with regard to the enforceability of the unsigned contract.
One of the presiding members of the NCAT Appeal Panel (Dyjecinska v Step-Up Renovations (NSW) Pty Ltd; Step-Up Renovations (NSW) Pty Ltd v Dyjecinska [2023] NSWCATAP 36), Principal Member Thode, held that the plain reading of section 10 of the Home Building Act does not require a signature. Only that the construction contract be in writing and with sufficiently described works. The Member stated that the provision was intended to prevent builders from enforcing unwritten contracts that were not sufficiently described.
Principal Member Thode held that:
"61. …the omission of a signature from an otherwise standard contract did not create uncertainty of the type requiring specific legislative intervention."
Additionally, the Principal Member considered it a "capricious argument" for the homeowner to rely on section 10 of the Home Building Act to prevent the builder from enforcing the contract but require the builder to remedy any defect or breach. The Member further expressed:
"This is particularly so in light of the Tribunal's decision at [122] that "the evidence strongly suggests that [the owner] refused to sign the contract" but permitted the builder to carry out the work."
This case is distinguished from others on this similar point. A simplified case analysis will help identify the main issues and corresponding ruling.
The NCAT Appeal Panel decision in Dyjecinska ([2023] NSWCATAP 36) distinguished these findings from a recent 2022 NCAT decision of Vujica v TNM Roofing Pty Ltd [2022] NSWCATAP 305. The Principal Member expressed at 59:
"For reasons of comity, it is preferable to follow the decisions of the Appeal Panel, but I consider Vujica sufficiently distinguishable from the present case as it did not concern a signed written contract."
| Issue | Ruling |
|---|---|
| Enforceability of Unsigned Contract | Contract enforceable despite the lack of signature |
| Compliance with Act | Contract complied with requirements for being in writing and sufficiently describing works |
| Aspect | Vujica Case | Dyjecinska Case |
|---|---|---|
| Contract Formation | Only a quotation identified as contract | Contract used Master Builders Association of NSW Residential Building BC4 Contract |
| Compliance with HB Act s 7(2) | Did not comply; not in writing and insufficient description of work | Complied; contract in writing and sufficiently described works |
| Appeal Panel's Interpretation | 'Writing' in s 10 should not be construed narrowly; must meet section 7 requirements | Unsigned contract enforceable as it met section 10 requirements for being in writing and sufficiently describing works |
These findings establish that NSW homeowners cannot avoid payment obligations simply because a contract remains unsigned if the contract otherwise meets the statutory requirements of being in writing and sufficiently describing the building works. The key factor is whether the homeowner's conduct demonstrated acceptance of the contract terms by permitting work to proceed. The NCAT Appeal Panel's findings were affirmed by the NSW Supreme Court in Dyjecinska v Step-Up Renovations (NSW) Pty Ltd [2024] NSWSC 159, reinforcing the binding authority of these principles.
The enforceability of unsigned contracts directly impacts whether homeowners must fulfil payment obligations for completed building work under the Home Building Act.
The Dyjecinska case highlights critical considerations for NSW homeowners entering into building agreements. While the unsigned contract was found enforceable in this instance, the ruling establishes important principles about contract formation and homeowner obligations.
First, homeowners cannot avoid payment obligations simply because they haven't signed a contract if they've permitted the builder to commence and carry out work. The Tribunal viewed the homeowner's conduct—allowing work to proceed without signing—as acceptance of the contract terms.
This conduct-based acceptance creates legally binding payment obligations even without formal signatures on residential building contracts.
Second, the contract must still comply with the Home Building Act's fundamental requirements: it must be in writing and sufficiently describe the building works. The MBA BC4 contract met these requirements even without signatures.
Contracts meeting these statutory requirements remain enforceable for payment purposes regardless of signature status under NSW construction law.
Third, homeowners who refuse to sign a contract but allow work to proceed face significant legal risks. The Tribunal may interpret this conduct as accepting the contract terms whilst attempting to avoid contractual obligations.
For NSW homeowners, this ruling reinforces the importance of obtaining specialist construction law advice before any building work commences. Understanding your contractual position and obligations at the outset prevents costly disputes and provides clarity about payment obligations, variation rights, and defects remedies.
The Dyjecinska ruling establishes specific circumstances when NSW homeowners must fulfil payment obligations despite unsigned contracts. Understanding these circumstances protects homeowners from inadvertently creating enforceable payment obligations.
Payment obligations arise when three conditions exist simultaneously. First, the contract must be documented in writing with sufficient detail describing the residential building work scope, specifications, and agreed terms. Second, the contract must comply with Home Building Act requirements including appropriate licensing disclosures, statutory warranties, and insurance documentation. Third, the homeowner's conduct must demonstrate acceptance of the contract terms by permitting the builder to commence and carry out the building work.
Homeowners who allow builders to proceed with alterations, additions, or construction work without signing contracts risk creating legally enforceable payment obligations. The Tribunal examines whether homeowners actively permitted work commencement, accepted builder attendance, or failed to object when building work commenced. These actions constitute conduct-based acceptance regardless of signature absence.
However, homeowners retain important protections under the Home Building Act even with unsigned contracts. Statutory warranty protections apply to residential building work regardless of contract signatures. Homeowners maintain rights to claim defective work remedies, pursue breach of contract claims, and enforce statutory warranty obligations. The contract's enforceability for payment purposes doesn't eliminate homeowner protections or builder obligations under NSW construction law.
Early legal advice helps homeowners understand whether unsigned contracts create payment obligations in their specific circumstances and what protections remain available under the Home Building Act.
When you work with Contracts Specialist, you receive legal advice directly from John Dela Cruz — Principal Lawyer with over 17 years of exclusive construction law experience.
John is an Australian Legal Practitioner and he services NSW, Queensland, Victoria, and Tasmania. He has dedicated his entire legal career to specialise in construction law. As a former Divisional President of the Master Builders Association NSW, he combines deep legal expertise with comprehensive industry knowledge. He maintains daily experience in building dispute tribunals (NCAT, VCAT, QCAT, TASCAT) and courts across multiple jurisdictions.
Unlike generalist lawyers who handle various legal matters, John specialises exclusively in construction law matters affecting homeowners, builders, contractors, and subcontractors. You receive focused expertise from a lawyer who understands both the legal framework and the practical realities of the building industry.
Yes, under certain circumstances. The Dyjecinska case established that an unsigned contract can be enforceable if it meets the Home Building Act requirements of being in writing and sufficiently describing the works. If a homeowner permits the builder to commence work without signing the contract, the Tribunal may find the homeowner accepted the contract terms through their conduct. However, each case depends on its specific facts and circumstances.
Section 10 of the Home Building Act 1989 (NSW) requires that a contract for residential building work must be in writing and sufficiently describe the work. The Dyjecinska case clarified that this section does not explicitly require signatures—only that the contract be documented in writing with adequate description of the building works to be performed.
The Dyjecinska case addressed this exact situation. The Tribunal found that allowing a builder to carry out work despite refusing to sign the contract may be interpreted as accepting the contract terms. The Tribunal considered it inconsistent for a homeowner to refuse contractual obligations whilst demanding the builder fulfil contractual obligations such as remedying defects. This conduct can result in the unsigned contract being enforceable against the homeowner.
The key distinction is the type of documentation involved. In Vujica v TNM Roofing [2022] NSWCATAP 305, only a quotation was provided, which didn't meet the Home Building Act requirements for being in writing and sufficiently describing the works. In Dyjecinska, the parties used a comprehensive MBA BC4 contract that detailed the works, even though it remained unsigned. The Vujica contract failed to comply with section 7(2) of the Act, whereas the Dyjecinska contract met those requirements despite lacking signatures.
Absolutely. The Dyjecinska case demonstrates the legal complications that arise from unsigned contracts. Signing a contract before work commences provides certainty for both parties about their rights and obligations. More importantly, you should obtain specialist construction law advice before signing any building contract to ensure the terms protect your interests and comply with NSW legislation. Early legal advice prevents expensive disputes and ensures you understand your contractual position from the outset.
If you're facing a building dispute involving an unsigned contract, seek specialist construction law advice immediately. The enforceability of your contract depends on specific factors including whether it's in writing, whether it sufficiently describes the works, and your conduct regarding the building work. A construction lawyer can assess your legal position, explain your rights under the Home Building Act, and advise on the best path forward—whether that's negotiation, tribunal proceedings, or another resolution strategy.
The Home Building Act provides consumer protections regardless of whether a contract is signed, but those protections depend on the contract meeting statutory requirements. Section 7 requires contracts to be in writing and sufficiently describe the work. Section 10 addresses enforceability of contracts. The Dyjecinska case established that these sections don't require signatures for enforceability. However, warranty provisions, licensing requirements, and other consumer protections under the Act still apply. It's essential to understand how these protections apply to your specific situation through specialist legal advice.
If you're facing a building dispute involving an unsigned contract or questions about your payment obligations under the Home Building Act, specialist construction law advice is essential. The Dyjecinska case demonstrates how contract enforceability depends on specific legal principles and your particular circumstances.
At Contracts Specialist, we provide NSW homeowners with clear guidance on their rights and obligations under residential building contracts. With over 17 years of exclusive construction law experience and daily NCAT tribunal practice, we understand how unsigned contracts affect your legal position and payment obligations.
Your free first consultation provides a clear assessment of your legal position with zero cost and zero obligation. We'll explain your rights under the Home Building Act, discuss your options, and recommend the best path forward for your specific situation.
Don't let uncertainty about an unsigned contract leave you vulnerable to unfair outcomes. Book your free consultation today to understand your legal rights and protect your interests in your NSW building project.
BOOK YOUR FIRST FREE CONSULTIf you’re a homeowner in New South Wales, it’s crucial to understand Construction Law to protect your investment. This ultimate guide to Construction Law is specifically designed to provide homeowners with essential insights into the legal landscape of home building in NSW.
If you’re a homeowner in New South Wales, it’s crucial to understand Construction Law to protect your investment. This ultimate guide to Construction Law is specifically designed to provide homeowners with essential insights into the legal landscape of home building in NSW.